Disney Performing Arts Center

Building California Construction Careers
Building California Construction Careers
Building California Construction Careers
Working in the Trades
What's Apprenticeship
Who Builds What
Find a Program
Pre-Apprenticeship
Women Can Build
One Stops
About BC3
California Construction
Links
Order
Contact Us
Disney Performing Arts Center

 

Project

Walt Disney Concert Hall - the Music Center's fourth venue and home of the Los Angeles Philharmonic and Los Angeles Master Chorale and the site for CalArts Theatre (REDCAT).

Location

111 South Grand Avenue
Los Angeles, CA 90012

Completion

October, 2003

Project Cost

$274 million

Building Size

293,000 square feet

Auditorium Seating Capacity

2,265 seats

Site Description

Walt Disney Concert Hall is situated on a 3.6 acre, full city block in the historic Bunker Hill section of Los Angeles. A large portion of the site will be dedicated to an urban park with expansive public gardens and ornamental landscaping.

Schedule

December 1999:

Construction Commencement

Spring 2001:

The first concrete pour of the roof of the main hall and the erection of the pre-cast concrete acoustical panels

Summer 2001:

Completion of the structural steel, including the framing of the main auditorium seating and erection of the six roof trusses

Summer 2001:

Commencement of installation of stainless steel panels on the exterior of the Concert Hall

Late 2002:

Completion of the curtain wall of the Concert Hall

Fall 2002:

Completion of the acoustical ceiling of the main auditorium

Fall 2003:

Completion

 
 